Check | Scenario Info

Check | Scenario Info

For greenpass Check one or more scenarios are needed. In total more than 30 parameters can be filled in the following 5 categories:


  • Building
  • Heating, Cooling and Energy
  • Open Space
  • Green Roofs and Facades
  • Trees

Note: The more detailed the input - the more detailed the output!

Building

The following building-related data can be entered.

Parameter

Definition

Entity

Footprint

Layout/ground plan area of all buildings

m2

Gross Floor Area

Gross Floor Area (GFA) 

m2

Height Ø

Average height of all buildings

m2

Number of Buildings

Total number of all buildings 

pcs.

Type

Building Status of project:

  • Stock
  • New

Selection

Construction Year

Year of building completion of project

Year

Asset Class

Asset class of project:

  • Residential
  • Commercial
  • Industrial

Selection

Asset Value

Asset value of project 


Heating, Cooling and Energy

The following energy-related data can be entered.

Parameter

Definition

Entity

Energy Source - Heating

Energy source of project for heating

  • Electricity
  • Gas
  • Oil
  • Wood Chips
  • Wood Pellets
  • District Heating
  • Others

Selection

Energy Demand  - Heating

Annual energy demand for heating (from EPC - energy performance certificate). Alternatively: Energy classes

kWh/m2a

Energy Price - Heating

Energy price of project for heating in €/kWh incl. VAT

€/kWh incl. VAT

Energy Source - Cooling

Energy source of project for cooling

  • Air Conditioning
  • District Cooling
  • Heat Pump
  • Others

Selection

Energy Demand  - Cooling

Annual energy demand for cooling (from EPC - energy performance certificate)

kWh/m2a

Energy Price - Cooling

Energy price of project for cooling

€/kWh incl. VAT

Energy Source - Electricity

Energy source of project for electricity:

  • Hydroelectric
  • Wind
  • Photovoltaic
  • Grid Mix
  • Others

Selection

Energy Demand  - Electricity

Annual energy demand for cooling (from EPC - energy performance certificate)

kWh/m2a

Energy Price - Electricity

Energy price of project for cooling

€/kWh incl. VAT

Photovoltaic

Performance of photovoltaic 

kWp

Solar Heat

Performance of solar 

kWh

Wind Power

Performance of generated wind power 

kWh


Open Space

The following open space-related data can be entered.

Parameter

Definition

Entity

Sealed Surfaces

Sealed area of project (e.g. asphalt, concrete, ...)

m2

Semi-permeable Surfaces

Semi-permeable area of project (e.g. drainage plaster, ...)

m2

Green Space

Green area of project (e.g. lawn, meadow, shrubs, ...)

m2

Blue Space

Blue space of project (e.g. lake, creek, biotope, sprinklers, fountains, ...)

m2


Green Roofs and Facades

The following building greenery-related data can be entered.


Parameter

Definition

Entity

Green Roof - Extensive

Extensive (<15 cm substrate height) green roof area of project

m2

Green Roof - Semi-intensive

Semi-intensive (15-30 cm substrate height) green roof area of project 

m2

Green Roof - Intensive

Intensive (>30 cm substrate height) green roof area of project

m2

Green Facade - ground-based

Area of grounded climbing plants (adult) on building within project

m2

Green Facade - planter-based

Area of plants in planters (adult) on building within project

m2

Green Facade - facade-based

Area of modular green wall and facade-greenery on building within project

m2


Trees

The following tree-related data can be entered.


Parameter

Definition

Entity

Tree - Small | 3m

Number of small trees with a height of <3m

pcs.

Tree - Medium | 6m

Number of moderate trees with a height of 6m

pcs.

Tree - Large | 10m

Number of large trees with a height of >10m

pcs.


    • Related Articles

    • Check | Rename Scenario

      To RENAME a scenario in greenpass Check, follow these steps: Go to the Project/Scenarios page. Open the Scenario Menu - this is located in the scenario bar next to the scenario name (see screenshot) Click RENAME or double-click on the scenario name ...
    • Check | Clone Scenario

      Use the CLONE function to duplicate a scenario within greenpass Check. To do this, go to the Project/Scenarios page. Open the Scenario Menu - this is located in the scenario bar next to the scenario name (see screenshot) Click CLONE to clone the ...
    • Check | Delete Scenario

      To delete a scenario in greenpass Check, follow these steps: Go to the Project/Scenarios page. Open the Scenario Menu - this is located in the scenario bar next to the scenario name (see screenshot) Click DELETE to delete the scenario. Attention: The ...
    • Check | Data Requirements

      To get results by greenpass Check the following data is needed: Project Data (e.g. name, adress, ...) needed for Climate Risks Scenario Data (e.g. building parameters, greenery, ...) needed for Climate Mitigation and Adaptation The parameters will be ...
    • Check | Data Collection - csv Form

      Use the csv form to collect your data for greenpass Check. Easily collect one or more projects or scenario data in one place and prepare and store your data locally. Output: .csv file Source: Local Download: greenpass Check | Data Input csv Form